Safety Inspection

Safety Management Standard

Research facilities for mass culture should comply with the following standard on installation and operation.

Installation Standard

Compliance Safety Management Level
1 2 3 4
Location of and Access to Laboratory Experiment zone for mass culture: separation (division) from general zone Recommended Recommended Mandatory Mandatory
Installation of locking equipment in the main gate (card, fingerprint recognition system, security system, etc.) - Recommended Mandatory Mandatory
Separation of door to controlled zone from other zones, using air-lock, equipment storage area, dressing room, or double-door - - Mandatory Mandatory
Installation of storage place to keep personal clothing and laboratory suit before entering laboratory Recommended Recommended Mandatory Mandatory
Separate installation of exclusive laboratory suit storage area and personal clothing storage area, through which access to laboratory is made - - Mandatory Mandatory
Installation of door or zone for transport of apparatus - Recommended Recommended Mandatory
Installation of door for transport of apparatus (manual control allowed) - Recommended Mandatory Mandatory
Experiment Zone Inside sealed zone: use of material that enables chemical sterilization and fumigation - - - Mandatory
Seam in sealed zone: use of shock-enduring material and coating for cleanliness - Recommended Recommended Mandatory
Seam in sealed zone: use of non-hardening sealant for complete sealing of facility - - Mandatory Mandatory
Air-conditioning Air inside sealed zone: maintenance of negative pressure and prevention of recirculation - - Mandatory Mandatory
Pressure difference between outside and maximum negative pressure zone: maintenance of -24.5Pa or over (±30% variation allowed) - - Mandatory Mandatory
Facility ventilation: at least 10 cycles per hour (at least 20 cycles per hour for Level 4 research facility) - Recommended Mandatory Mandatory
Installation of air supply system connected to exhaust system - - Mandatory Mandatory
Installation of HEPA filter in air supply duct - - Recommended Mandatory
Installation of HEPA filter in exhaust duct (two-layer HEPA filter for Level 4 research facility) - - Mandatory Mandatory
Installation of reserve exhaust filter box - - Recommended Mandatory
Installation of airtight damper in front end of exhaust HEPA filter (installation of bubble-tight damper or at least equivalent damper for Level 4 research facility) - - Mandatory Mandatory
Front end duct of exhaust HEPA filter and exhaust HEPA filter box: enduring pressure of 1,000Pa or over (air leak rate of within 10%) (enduring pressure of 2,500Pa or over (air leak rate of within 1%) for airing HEPA filter box and duct in Level 4 research facility) - - Mandatory Mandatory
Experimenter Safety Protection Installation of hand sterilizer and eye washer in laboratory Recommended Recommended Mandatory Mandatory
Installation of emergency shower facility in close location to dressing zone for taking off contaminated laboratory suit - Recommended Recommended Mandatory
Experiment Apparatus Installation of autoclave (installation of double door autoclave for Level 3∙4 research facility) Mandatory Mandatory Mandatory Mandatory
Installation of biosafety cabinet - Recommended Mandatory Mandatory
Use of centrifuge capable of preventing leak of aerosol - Recommended Mandatory Mandatory
Design for LMO leak prevention. Installation of culture equipment capable of sterilization control in closed state. Inspection of sealing status right after installation of culture device and on a regular basis - Recommended Mandatory Mandatory
Installation of bacteriostatic filter or bacteriostatic device having at least equivalent effect in exhaust pipe of culture device. Performance inspection right after installation and on a regular basis - Mandatory Mandatory Mandatory
Inspection of sealing status and performance of any equipment and device in case that any part of it related to sealing is modified or replaced - Mandatory Mandatory Mandatory
Installation of sealing status detection equipment for culture equipment and any device directly connected to it - - Recommended Mandatory
Waste Treatment Solid waste: installation of facility that can remove biological activation, such as autoclave or chemical processing Recommended Mandatory Mandatory Mandatory
Waste water from experiment: installation of facility that can remove biological activation, such as autoclave or chemical processing Recommended Mandatory Mandatory Mandatory
Exhaust through HEPA filter - Recommended Mandatory Mandatory
Other Facilities Installation of communication equipment connected to the outside of facility Recommended Recommended Mandatory Mandatory
Installation of back draft prevention equipment for pipe - Recommended Mandatory Mandatory
Installation of DOP nozzle of exhaust HEPA filter box - - Mandatory Mandatory
Installation of observable inner pressure gauge and warning equipment - - Mandatory Mandatory
Installation of reserve power supply facility for air-conditioning and mandatory facility in case of blackout - - Mandatory Mandatory
Operation Standard
Compliance Safety Management Level
1 2 3 4
Access to Experiment Zone Keep door to laboratory always closed. Allow only approved persons to enter. Recommended Mandatory Mandatory Mandatory
Place and record access card. - Recommended Mandatory Mandatory
Place and use protective equipment such as exclusive laboratory suit. Recommended Recommended Mandatory Mandatory
Attach biosafety marking (LMO name, safety management level, name and contact of facility manager, etc.) in front of door. Recommended Mandatory Mandatory Mandatory
Activity in Experiment Zone Wash hands upon finishing experiment or exiting mass culture experiment zone. Mandatory Mandatory Mandatory Mandatory
Wear laboratory suit in experiment zone. Take off laboratory suit before moving to general zone. Recommended Mandatory Mandatory Mandatory
Use mechanical pipette during experiment. Mandatory Mandatory Mandatory Mandatory
Minimize occurrence of aerosol during experiment. Recommended Mandatory Mandatory Mandatory
Prohibit food consumption, food preservation, smoking and makeup application in experiment zone. Mandatory Mandatory Mandatory Mandatory
Prohibit carry-in of articles irrelevant to experiment, such as plants, animals and clothes. Recommended Mandatory Mandatory Mandatory
Check sealing status of culture container at least once a day if culture experiment is underway. - - Mandatory Mandatory
Pay attention to any contamination during inoculation into culture equipment, sampling and transport. (Sterilize instantly upon contamination.) - - Mandatory Mandatory
Sterilize biosafety cabinet, bacteriostatic filter of other equipment, etc. right before replacement and during regular inspection. - - Mandatory Mandatory
Establish management method for insects or rodents. Mandatory Mandatory Mandatory Mandatory
Wear laboratory suit for mass culture experiment in laboratory. Take off laboratory suit upon exit and take shower to remove contamination - - Recommended Mandatory
Biosafety LMO storage (refrigerator, freezer, etc.): attach "Biohazard" marking, etc. Mandatory Mandatory Mandatory Mandatory
Attach marking to culture equipment, etc. running for mass culture experiment according to the level - Mandatory Mandatory Mandatory
Organize biosafety committee and appoint biosafety management director. Recommended Mandatory Mandatory Mandatory
Designate biosafety manager. Recommended Recommended Mandatory Mandatory
Conduct and attend education on biosafety. Recommended Mandatory Mandatory Mandatory
Manage and keep record related to installation and operation of research facility. Mandatory Mandatory Mandatory Mandatory
Record and keep LMO storage and management document. Mandatory Mandatory Mandatory Mandatory
Write, report and keep record about infection accidents that occur during experiment. - Recommended Mandatory Mandatory
Keep inspection record and operation record as well as serial ID number for each piece of facility and device - - Recommended Mandatory
Establish and apply biosafety management regulation. (Establish facility operation regulation separately for Level 3∙4 research facility.) Recommended Mandatory Mandatory Mandatory
Collect and keep normal serum of persons engaging in test and research. (Conduct serum collection and health checkup on a regular basis, if needed.) - Recommended Recommended Mandatory
Experimenter Safety Protection Contaminated waste before treatment: keep it in separate safe location or container. Recommended Mandatory Mandatory Mandatory
Deactivate any waste material and waste liquid generated from culture equipment, culture medium, contaminated equipment and device, and organisms related to mass culture experiment before disposal, after finishing mass culture experiment. Recommended Mandatory Mandatory Mandatory
Establish regulation on laboratory waste treatment. Mandatory Mandatory Mandatory Mandatory

Note : As for safety management levels, research facilities for mass culture are classified into GLSP(Good Large Scale Practice), Level 1, Level 2 and Level 3, each corresponding to Level 1, Level 2, Level 3 and Level 4 prescribed in Attached Table 1 of the Enforcement Decree.